How to submit an aerobic maintenance report in Kimble County, Texas

Kimble County’s permitting authority is Kimble County ((830) 591-6970, theranchoutfit@yahoo.com). The county has not published how maintenance providers submit the §285.91 report; most Texas authorities accept email or a document upload, and some run a portal.

Reports are due within 14 days after the test (30 TAC §285.7(e)(1)(B)).

We are confirming the channel — if you file here, tell us how, using the form below.

Kimble County at a glance

Permitting authority Kimble County
Type County
TCEQ authorized-agent number 620119
How reports are filed Not published
Portal —
Channel confirmed? Not yet — help us confirm it
OSSF authorizations, 2025 38
Aerobic permits, 2015–2025 18
Aerobic share of 2025 permits 7.9%
Licensed maintenance providers 0
Licensed maintenance technicians 0
Rank by aerobic permits 140 of 254

What every Texas report must contain

  • ·The date of the visit and the name and licence number of the provider or technician who made it
  • ·The system owner, the address and the permit number
  • ·Readings taken: chlorine residual, effluent quality, sludge and scum where applicable
  • ·Whether the disinfection device held an adequate supply
  • ·Any maintenance, repair or part replaced during the visit
  • ·What the owner was told to do, and the provider’s signature

From 30 TAC §285.91(4), Table IV. The full list is on what a Texas maintenance report must contain.

The two clocks

A conventional aerobic system with surface application is tested every four months, and each report is filed within 14 days of the test — to Kimble County and to the owner. Miss the second clock and the visit still happened, but the record says it did not.

Permits in Kimble County, 2015–2025

YEAR ALL OSSF SURFACE (SPRAY) DRIP
2015 6 0 0
2016 4 0 0
2017 16 1 0
2018 9 0 0
2019 8 0 0
2020 22 1 0
2021 9 3 0
2022 12 2 0
2023 251 2 0
2024 18 5 1
2025 38 3 0

Authorizations to Construct reported by every authorized agent covering Kimble County. Surface irrigation and drip both require aerobic pretreatment; together they are the 18 aerobic systems above. The statewide dataset has all 254 counties.

Is this out of date?

If you file in Kimble County and this is wrong — or if it is right and we have it marked unconfirmed — tell us and we will correct it. This is the only way the 248 unconfirmed counties get confirmed.

Summarizes public records as of Oct 5, 2026: the TCEQ authorized-agent register, the OSSF licence register, and the county’s own published pages. Not legal advice — verify with your permitting authority.