How to submit an aerobic maintenance report in Fort Bend County, Texas

Fort Bend County’s permitting authority is Fort Bend County. Maintenance providers submit the 30 TAC §285.91 report through the county’s online portal.

MyHD Customer Portal: maintenance inspections are entered directly ('Enter Records Directly') or bulk-loaded with 'Launch Data Wizard' from a .csv, .tsv or .txt file; maintenance contracts are uploaded one at a time. May 2025 notice to a third-party records product users: export the CSV and upload it to the county's online portal; county stopped collecting inspection data by other routes on 3/19/25. The 14-day filing rule and refusal of fax/mail are reported from prior notes, not seen on the fetched pages.

Reports are due within 14 days after the test (30 TAC §285.7(e)(1)(B)). Verified Oct 5, 2026.

Source: https://www.fortbendcountytx.gov/sites/default/files/document-central/document-central/environmental-health-documents/forms-library/OSSF-Customer-Portal---How-To-Guide.pdf

Fort Bend County at a glance

Permitting authority Fort Bend County
Type County
TCEQ authorized-agent number 620076
Phone 281-342-7469
How reports are filed portal
Portal MyHD Customer Portal
Channel confirmed? Yes, Oct 5, 2026
OSSF authorizations, 2025 463
Aerobic permits, 2015–2025 5,470
Aerobic share of 2025 permits 99.6%
Licensed maintenance providers 23
Licensed maintenance technicians 15
Rank by aerobic permits 17 of 254

What every Texas report must contain

  • ·The date of the visit and the name and licence number of the provider or technician who made it
  • ·The system owner, the address and the permit number
  • ·Readings taken: chlorine residual, effluent quality, sludge and scum where applicable
  • ·Whether the disinfection device held an adequate supply
  • ·Any maintenance, repair or part replaced during the visit
  • ·What the owner was told to do, and the provider’s signature

From 30 TAC §285.91(4), Table IV. The full list is on what a Texas maintenance report must contain.

The two clocks

A conventional aerobic system with surface application is tested every four months, and each report is filed within 14 days of the test — to Fort Bend County and to the owner. Miss the second clock and the visit still happened, but the record says it did not.

Permits in Fort Bend County, 2015–2025

YEAR ALL OSSF SURFACE (SPRAY) DRIP
2015 508 425 77
2016 483 409 66
2017 449 374 72
2018 470 367 99
2019 452 362 84
2020 547 446 92
2021 634 511 121
2022 565 441 121
2023 459 363 92
2024 487 409 78
2025 463 389 72

Authorizations to Construct reported by every authorized agent covering Fort Bend County. Surface irrigation and drip both require aerobic pretreatment; together they are the 5,470 aerobic systems above. The statewide dataset has all 254 counties.

Is this out of date?

If you file in Fort Bend County and this is wrong — or if it is right and we have it marked unconfirmed — tell us and we will correct it. This is the only way the 248 unconfirmed counties get confirmed.

Summarizes public records as of Oct 5, 2026: the TCEQ authorized-agent register, the OSSF licence register, and the county’s own published pages. Not legal advice — verify with your permitting authority.